The Gamsberg Project will exploit one of the largest known undeveloped zinc orebodies in the world and will comprise an open-pit mine with a dedicated processing plant.
B&W’s Overall Scope of Work
Period 2017 – 2019
Site Manhours 732,416
Peak Manpower 442
Description:
Electrical, instrumentation, hook-ups, and commissioning.
Power distribution, sub-station, and switchyard.
Project management and design of power distribution and switchyards.
Four-month peak successfully executed.
Gamsberg Zinc Mining & Concentrator Project
A critical feature of Gamsberg’s development is its approach to biodiversity. The project was developed in the ecologically sensitive succulent Karoo biome, one of just 35 “biodiversity hotspots” in the world. This required extensive engagement with key stakeholders – government, NGOs, and landowners, which has resulted in a unique biodiversity offset agreement.
The Gamsberg Project’s total value was estimated at 400 million US$, for a complete and functioning zinc processing plant. Construction of the process plant and vital infrastructure to support the overall project, including a power line, water pipeline, and high-density polyethylene (HDPE)-lined tailings dam. During execution, the project peaked at approximately 2,300 site personnel, administration, and support staff.
Contract Value R110.0 million
Period February 2017 – July 2018
Gamsberg 66kV OHL & 66kV Substation
B&W designed, constructed and commissioned a 19.5km, 66kV, 45MVA steel monopole power line with OPGW for the Gamsberg Project. We also designed, constructed and commissioned the 66/11kV Main receiving and step down substation, consisting of:-
- Incoming breakers and surge arrestors;
- Double bus supply arrangement to;
- Two 45kVA, 66/11kV transformers;
- 66kV yard protection and switching panels;
- 11kV feeder panels;
- Power factor correction;
- Substation automation system with scada.
Additional work included the extension of the 11kV power supply, from the Storm water management pond overhead line terminal point (Gamsberg Mountain Bottom) to top of the mountain for powering up radio infrastructure on the 21m mast, 100kVA transformer pole mounted 11kV/400V.
Reticulation Contractor of the year was awarded to B&W at the 2018 ECA Presidential Excellence Awards.
Gamsberg Concentrator & Process Plant
Contract Value R220.0 million
Period November 2017 – February 2019
Electrical Cable 235,000m
Instrument Cable 80,000m
Cable Racking 25,000m
Instruments 2,400
Lights 1,500
Gamsberg Concentrator & Process Plant
Black Mountain Mining, a part of the global Vedanta Resources Plc, appointed an EPCM contractor to execute the Gamsberg Zinc Mining and Contractor Project located in Aggeneys, South Africa.
The duty specification was to assist Black Mountain Mining with setting up a Process Plant with suitable capacity for processing the zinc ore to produce saleable grade zinc concentrate for export of the concentrate along with the development of associated infrastructure and utilities such as raw water and power to the site and mining infrastructure.
Black Mountain Mining developed a Greenfield zinc mine project at Gamsberg consisting of an open cast mine, ore beneficiation plant and associated infrastructure.
Gamsberg project is one of the most strategic projects of Zinc International business of Vedanta Resources Plc. The Gamsberg deposit consists of an open pit zinc mine with a defined ore resource of 186 million tons and over 250 million tone of potential ore resources.
The Gamsberg mine is located in the Northern Cape Province of South Africa, just south of the N14 National Road linking Upington to Springbok and 20km east of the existing Black Mountain Mine and the town of Aggeneys. The site is characterized by an oval shaped Inselberg approximately 220 meters above the surrounding plains.
B&W was presented with the Award for Safety Excellence in recognition of Zero LTI’s, pro-active safety behaviour and safety risk management in 2019.
Contract Value R15.3 million
Period November 2017 – July 2018
Gamsberg Water Works
B&W was awarded the Electrical and Instrumentation (E&I) Water Package on the Gamsberg Zinc Concentrator Project.
B&W was responsible for the supply, delivery, off-loading, handling, storing, installation, functional testing, commissioning and hand-over of the following
Site-wide equipment:
- 11kV cables installed in ground and on racks including terminations;
- 3.3kV cables installed in ground and on racks including terminations;
- Low voltage cables installed in ground and on racks including terminations;
- BCEW installed with MV and LV cables including terminations;
- Control and instrumentation cables including fibre optic cables installed in sleeves and on racks including terminations;
- Cable racks and accessories including support steelwork;
- Site-wide earthing installation;
- Pump station earthing installations;
- Area lighting systems;
- Solar power system for RTU panels.
Equipment inside buildings and pump stations:-
- Small power installation
- Cable racks;
- Switched socket outlets;
- Isolators;
- STOP/START/E-STOP stations;
- Cabling and wiring;
- Lighting installations;
- Fire detection equipment;
- Fire protection equipment;
- Welding plugs;
- Earthing and lightning protection equipment;
- All instruments.
Commissioning included:-
- 11kV/3.3kV, 2500kVA Transformers;
- 3.3kV/400V, 315kVA Transformers;
- 400V Motor Control Centres and Local Control Panels;
- 400V Stop/Start/E-Stop Stations;
- UPSs and Batteries;
- Low Voltage Free Standing VSD’s.
Pre-Commissioning included:-
- PLC Cabinet;
- RIO Panels;
- RTU Panels;
- Operator/Control Stations.
Contract Value R6.0 million
Period October 2018 – March 2019
Gamsberg Mining Access Road Street Lighting
Black Mountain Mining appointed B&W to design, supply and install north access ramp lighting.
The scope of work included:-
- Design 1610m of LED street lighting for both the LDV and HME lanes;
- Supply and install LED street lights for both LDV and HME lanes;
- Supply and install 2 kiosks (1 for LDV lane and 1 for HME lane);
- Excavate trenching in soft/hard soil;
- Supply and install cables – bundle conductor;
- Terminate cables;
- Supply and install main feeder cable from MS3.